24-3116
Request for approval of a change in contract with Blazey Construction Services, LLC, in connection with Tower Oaks Plaza Subdivision drainage improvements - 2018, adding 180 calendar days, with an addition in the amount of $42,264.21, Job No. 23/0027, UPIN 19103MF14801, Precinct 3, MWDBE Contracted Goal: 31%, MWDBE Current Participation: 100%.
What this record is
- Held by
- Blazey Construction Services, LLC 13 records across this site
- Amount
- $42K
- Runs until
- no end date published in this record
- Type
- contract
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Blazey Construction Services, LLC also holds
Request for approval of a change in contract with Blazey Construction Services, LLC, in connection with final construction of Tower Oaks Plaza Subdivi… Request for approval of a change in contract with Blazey Construction Services, LLC, in connection with Tower Oaks Plaza Subdivision - 2018, with an a… Transmittal by the Office of the County Engineer of a substantial completion certificate with Blazey Construction Services, LLC, in connection with To… Request for approval of a change in contract with Blazey Construction Services, LLC, in connection with Tower Oaks Plaza Subdivision Drainage Improvem… Request for approval of a change in contract with Blazey Construction Services, LLC, in connection with final construction of Evergreen Villas Subdivi…All 13 records for Blazey Construction Services, LLC →
- Committee
- Commissioners Court
- Requested by
- County Engineer
- Introduced
- May 20, 2024
- On agenda
- June 4, 2024
- Passed
- June 4, 2024