docketcity.com
24-2906

Request for approval of a change in contract with Allgood Construction Co., Inc., in connection with W. Gulf Bank Road from I45 to Airline Drive, adding 98 calendar days, with an addition in the amount of $56,525.83, Job No. 22/0461-3, UPIN 19101MF0XV01, Precinct 2, MWDBE Contracted Goal: 25%, MWDBE Current Participation: 59.11%.

Contract - Amendment Passed Introduced April 30, 2024

What this record is

Held by
Allgood Construction Co., Inc 14 records across this site
Amount
$57K
Runs until
no end date published in this record
Type
contract
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Allgood Construction Co., Inc also holds

Request for approval of a change in contract with Allgood Construction Co., Inc., in connection with final construction of West Gulf Bank Road from I4… $947K Harris County, TX Request for approval of a change in contract with Allgood Construction Co., Inc., in connection with West Gulf Bank Road from I45 to Airline Drive, ad… Harris County, TX Request for approval of a change in contract with Allgood Construction Co., Inc., in connection with West Gulf Bank Road from I45 to Airline Drive, wi… $469K Harris County, TX Request for approval of a change in contract with Allgood Construction Co., Inc., in connection with West Gulf Bank Road from I45 to Airline Drive, wi… $11K Harris County, TX Request for approval of a change in contract with Allgood Construction Co. Inc., in connection with West Gulf Bank Road from I45 to Airline Drive, wit… $67K Harris County, TX

All 14 records for Allgood Construction Co., Inc →

Committee
Commissioners Court
Requested by
County Engineer
Introduced
April 30, 2024
On agenda
June 4, 2024
Passed
June 4, 2024

Where it was heard

Commissioners Court Jun 4, 2024 approved Pass