Request for approval of a change in contract with TB Concrete Construction in connection with final construction of W. Montgomery, TC Jester and W. Mount Houston Roads - 2018, adding 289 calendar days, with an addition in the amount of $88,810.49, Job No. 21/0106-2, UPIN 19101MF0Y201, Precincts 1 & 2, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County’s M/WBE Program.
What this record is
- Held by
- TB Concrete Construction
- Amount
- $89K
- Runs until
- no end date published in this record
- Type
- award
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Commissioners Court
- Requested by
- County Engineer
- Introduced
- April 24, 2024
- On agenda
- May 7, 2024
- Passed
- May 7, 2024