docketcity.com
24-2614

Request for approval of a change in contract with Reliance Construction Services, LP, in connection with Water Distribution System - Parkwood Estates Ph 3 Apala Dr - 2021, adding 90 calendar days, Job No. 22/0423-1, UPIN 21289MF1Y601, Precinct 2, MWDBE Contracted Goal: 100%, MWDBE Current Participation: 100%.

Contract - Amendment Passed Introduced April 22, 2024

What this record is

Held by
Reliance Construction Services, LP 21 records across this site
Runs until
no end date published in this record
Type
contract
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Reliance Construction Services, LP also holds

Request for approval of a change in contract with Reliance Construction Services, LP, in connection with final construction of Water Distribution Syst… $241K Harris County, TX Request for approval of a change in contract with Reliance Construction Services, LP, in connection with final construction of Water Distribution Syst… $76K Harris County, TX Request for approval of a change in contract with Reliance Construction Services, L.P., in connection with Beaumont Place Phase II Subdivision Drainag… $526 Harris County, TX ORDINANCE approving and authorizing contract with RELIANCE CONSTRUCTION SERVICES, L.P. to provide Construction Services for FY2026 Ditch Re-Establishm… $9.00M Houston, TX ORDINANCE appropriating $5,730,000.00 out of Water & Sewer System Consolidated Construction Fund; approving and authorizing contract with RELIANCE CON… Houston, TX

All 21 records for Reliance Construction Services, LP →

Committee
Commissioners Court
Requested by
County Engineer
Introduced
April 22, 2024
On agenda
May 7, 2024
Passed
May 7, 2024

Where it was heard

Commissioners Court May 7, 2024 approved Pass