Request for approval of a change in contract with Durwood Greene Construction, Co., in connection with Clay Road 2 - West of Porter Road to West of Ventana Prairie Drive, adding 236 calendar days, with an addition in the amount of $445,403.69, Job No. 21/0155-2, UPIN 171033954822, Precinct 4, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County’s M/WBE Program.

Contract - Amendment Passed Introduced April 22, 2024

What this record is

Held by
Durwood Greene Construction 4 records across this site
Amount
$445K
Runs until
no end date published in this record
Type
award
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Durwood Greene Construction also holds

ORDINANCE appropriating $50,656,043.10 out of Dedicated Drainage and Street Renewal Capital Fund - Ad Valorem Tax; approving and authorizing contract … Houston, TX Request for approval of a change in contract with Durwood Greene Construction Co., in connection with final construction of Clay Road 2 - West of Port… $40K Harris County, TX Request for approval of a change in contract with Durwood Greene Construction Co., in connection with final construction of Asphalt Package 2022-1, wi… $420K Harris County, TX
Committee
Commissioners Court
Requested by
County Engineer
Introduced
April 22, 2024
On agenda
May 7, 2024
Passed
May 7, 2024

Where it was heard

Commissioners Court May 7, 2024 approved Pass