Request for approval of change in contract No. 2 with Lecon, Inc., for the Zube Storm Water Detention Basin Phase 3, adding 89 calendar days and resulting in an addition of $300,810.60 to the contract amount. (Little Cypress Creek Watershed, Bond ID F-27, Project ID L500-01-00-E003, Job No. 21/0240, Precinct 4, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County’s M/WBE Program).

Contract - Amendment Passed Introduced February 14, 2024
Committee
Commissioners Court
Requested by
Flood Control
Introduced
February 14, 2024
On agenda
February 27, 2024
Passed
February 27, 2024

Where it was heard

Commissioners Court Feb 27, 2024 approved Pass