Change Order/Amendment No. 5 with Modern Contractors for Fleet Services Center Additions and Renovations (Phase Two) in the amount of $176,052.11 for plumbing additions and deletions, adjustment of construction manager contract costs, electrical work for EV charging stations, structural additions, expansion of new concrete parking/sidewalk surface, extended irrigation, mechanical/electrical coordination, added door hardware, fire extinguishers, soil chemical injection, protective bollards and millwork revisions.
What this record is
- Held by
- Modern Contractors 24 records across this site
- Amount
- $176K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Modern Contractors also holds
Change Order/Amendment No. 4 with Modern Contractors for Fleet Services Center Additions and Renovations (Phase Two) in the amount of $42,378.86 for d… Change Order/Amendment No. 3 with Modern Contractors for Fleet Services Center Additions and Renovations (Phase Two) in the amount of $216,603.44 for … Change Order/Amendment No. 2 with Modern Contractors for Fleet Services Center Additions and Renovations (Phase Two) in the amount of $171,170.06 for … Fleet Service Center Phase One Change Order/Amendment No. 8 with Modern Contractors in the amount of $93,212 for temporary office trailer annual maint… Change Order/Amendment No. 1 with Modern Contractors in the amount of $5,471,711 for the balance of construction cost for Phase Two Additions and Reno…All 24 records for Modern Contractors →
- Committee
- Engineering
- Introduced
- May 22, 2020
- On agenda
- June 2, 2020
- Passed
- June 2, 2020