Ordinance amending the FY 2019/2020 Capital Improvement Projects Budget; construction contract with Gra-Tex Utilities in the amount of $2,558,259 for sanitary sewer and electrical improvements at Loyd Park; material testing with Kleinfelder Consultants in the amount of $23,513; contract contingency in the amount of $127,913; In-house labor distribution in the amount of $127,913 for a total project cost of $2,837,598

Ordinance Adopted Introduced December 20, 2019

What this record is

Held by
Gra-Tex Utilities 9 records across this site
Amount
$2.56M
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Gra-Tex Utilities also holds

Final Reconciliation Amendment (Change Order) No.2 to construction contract with Gra-Tex Utilities for Miscellaneous Water and Wastewater Improvements… $87K Grand Prairie, TX Change Order No. 1 for Construction Contract with Gra-Tex Utilities, in the amount of $65,290, for sanitary sewer and electrical improvements at Loyd … $65K Grand Prairie, TX Amendment (Change Order) No.1 to construction contract with Gra-Tex Utilities for Miscellaneous Water and Wastewater Improvements in the net total neg… $224K Grand Prairie, TX Ordinance amending the FY 2018/2019 Capital Improvement Projects Budget; Construction Change Order/Amendment No. 1 Gra-Tex Utilities, Inc. in the amou… $63K Grand Prairie, TX Ordinance amending the FY 2018/2019 Capital Improvement Projects Budget; Construction contract with Gra-Tex Utilities, Inc. in the amount of $314,097.… $314K Grand Prairie, TX

All 9 records for Gra-Tex Utilities →

Committee
Engineering
Introduced
December 20, 2019
On agenda
January 7, 2020
Passed
January 7, 2020
Enacted
January 7, 2020
Enactment no.
ORD 10785-2020