19-8769
Contract with Birkhoff, Hendricks and Carter, LLP in the amount of $110,300, plus a 5% contingency of $5,515 for a total of $115,815 for the detailed design, bidding assistance and construction administration for a new material storage bunker building and additional concrete pavement at the existing Water Utilities Service Facility located at 620 Small Hill (at Beltline)
What this record is
- Amount
- $110K
- Runs until
- no end date published in this record
- Type
- contract
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Public Works
- Introduced
- March 7, 2019
- On agenda
- March 19, 2019
- Passed
- March 19, 2019