Change Order/Amendment No. 2 with Hill & Wilkinson General Contractors in the amount of $1,885,000 for the balance of construction cost for the Firehouse Gastro Park restaurant; 5% contingency in the amount of $90,000; $2,500 allowance for additional geotechnical consultation and construction testing; plus a $5,000 allowance for audio/visual (A/V) provisions for a total funding request in the amount of $1,982,500

Agenda Item Consent Agenda Introduced October 5, 2018

What this record is

Held by
Hill & Wilkinson General Contractors 20 records across this site
Amount
$1.89M
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Hill & Wilkinson General Contractors also holds

Change Order/Amendment No. 5 with Hill & Wilkinson General Contractors for City Hall Municipal Campus Phase Two construction work in the amount of $98… $98K Grand Prairie, TX Change Order/Amendment No. 4 with Hill & Wilkinson General Contractors for City Hall Municipal Campus Phase Two construction work in the amount of $10… $104K Grand Prairie, TX Change Order/Amendment No. 3 with Hill & Wilkinson General Contractors for the City Hall Municipal Campus Phase Two construction work, in the amount o… $76K Grand Prairie, TX Construction Manager at Risk (CMAR) Contract with Hill & Wilkinson General Contractors (H&W) in the amount of $6,878,130 for the initial phase of cons… $6.88M Grand Prairie, TX Change Order/Amendment No. 2 with Hill & Wilkinson General Contractors for the City Hall Municipal Campus Phase Two construction work in the amount of… $109K Grand Prairie, TX

All 20 records for Hill & Wilkinson General Contractors →

Committee
Engineering
Introduced
October 5, 2018
On agenda
October 16, 2018
Passed
October 16, 2018