18-8173
Construction contract with North Rock Construction for the rehabilitation of two bridges over Fish Creek in the amount of $673,836, plus a 5% contingency amount of $33,692, for a total project cost of $707,528
What this record is
- Held by
- North Rock Construction 3 records across this site
- Amount
- $674K
- Runs until
- no end date published in this record
- Type
- contract
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
North Rock Construction also holds
Approval of Bid Award for the Construction of the LLELA Kayak Launch to North Rock Construction, LLC, in the Amount of $721,826.01; and Authorization … Amendment/Change order No. 3 with North Rock Construction, LLC in the amount of $47,889.47 for the rehabilitation of two bridges over Fish Creek locat…- Committee
- Public Works
- Introduced
- August 15, 2018
- On agenda
- September 4, 2018
- Passed
- September 4, 2018