18-8080
Ordinance amending the FY 2017/2018 Capital Improvement Projects Budget; Construction contract with RKM Utility Services, Inc. for Paving, Drainage, Water and Wastewater Improvements to Acosta Street from Nunez to Cober, in the total amount of $1,293,459; material testing with Reed Engineering Group in the amount of $19,802.75; in-house engineering in the amount of $64,672.95; and 5% construction contract contingency in the amount of $64,672.95; for a total project cost of $1,442,607.65
What this record is
- Held by
- RKM Utility Services, Inc 2 records across this site
- Amount
- $1.29M
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
RKM Utility Services, Inc also holds
Final Reconciliation Amendment/Change Order No. 5 with RKM Utility Services, Inc..for Paving, Drainage, Water and Wastewater Improvements for Acosta S…- Committee
- Engineering
- Introduced
- July 24, 2018
- On agenda
- August 7, 2018
- Passed
- August 7, 2018
- Enacted
- August 7, 2018
- Enactment no.
- ORD 10503-2018