docketcity.com
17-7091

Construction contract with Guerrero’s Construction for drainage improvements at 20th Street and Walnut in the total amount of $418,302.50; material testing with Reed Engineering Group in the amount of $13,723.00; in-house engineering in the amount of $20,915.13; and 5% construction contract contingency in the amount of $20,915.13; for a total project cost of $473,855.76

Agenda Item Consent Agenda Introduced August 21, 2017

What this record is

Held by
Guerrero’s Construction 3 records across this site
Amount
$418K
Runs until
no end date published in this record
Type
contract
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Guerrero’s Construction also holds

Change Order No. 1 with Guerrero’s Construction for drainage improvements at 20th Street and Walnut, in the total amount of $43,625 $44K Grand Prairie, TX Construction contract with Guerrero’s Construction for Miscellaneous Drainage Improvements at Section 1-Lake Parks West Drainage Flume from Spillway t… $156K Grand Prairie, TX
Committee
Engineering
Introduced
August 21, 2017
On agenda
September 5, 2017
Passed
September 5, 2017