17-6951
Ordinance amending the FY 2016/2017 Capital Improvement Projects Budget and the Park Venue Fund; Construction contract to Layne in the base bid amount of $1,198,814.00 and add alternate #2 in the amount of $84,329.00 for a total construction contract amount of $1,283,143.00 for the construction of an irrigation well at Central Park; Material testing with Alliance Geotechnical Group in the amount of $6,040; 5% contract contingency in the amount of $64,157; In-house engineering in the amount of $64,157 for a total project cost of $1,417,497.00
What this record is
- Held by
- Alliance Geotechnical Group 14 records across this site
- Amount
- $84K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Alliance Geotechnical Group also holds
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Alliance Geotechnical Group, Inc. for Materials Testing S… Request for approval to negotiate a professional services agreement with Alliance Geotechnical Group, Inc. for Construction Materials Testing (CMT) an… Request for approval to execute an agreement with Alliance Geotechnical Group, Inc., in the amount of $56,851.00 for Professional Engineering Services… Request by the Office of the Purchasing Agent for approval of an award on the basis of successful negotiations with the highest overall evaluation and… Consider approval of a Professional Services Agreement with Alliance Geotechnical Group; for geotechnical materials testing services associated with t…All 14 records for Alliance Geotechnical Group →
- Committee
- Public Works
- Introduced
- July 11, 2017
- On agenda
- August 1, 2017
- Passed
- August 1, 2017
- Enacted
- August 1, 2017
- Enactment no.
- ORD 10314-2017