17-6911

Construction contract with Excel 4 Construction LLC in the amount of $375,319.00 for the W.E. Roberts St. Water and Wastewater Improvements project; material testing with Alliance Geotechnical Group in the amount of $12,423; 5% contract contingency in the amount of $18,766; in-house labor distribution in the amount of $18,766, for a total project cost of $425,274

Agenda Item Consent Agenda Introduced July 7, 2017

What this record is

Held by
Excel 4 Construction LLC 8 records across this site
Amount
$375K
Runs until
no end date published in this record
Type
contract
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Excel 4 Construction LLC also holds

Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Change Order with Excel 4 Construction, LLC, for the Construction of th… McKinney, TX Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract and All Necessary Change Orders with Excel 4 Construction, LLC… McKinney, TX **Approval of Change Order No. 2 with Excel 4 Construction, LLC for the Reconciliation of Quantities for the City of Richland Hills, Texas 48th Year C… Tarrant County, TX Resolution - A Resolution Authorizing Funding for an Amount Not to Exceed $350,000.00 and Awarding a Contract for the Construction of a Community Deve… $350K Mansfield, TX Final Reconciliation Change Order/Amendment #6 with Excel 4 Construction, LLC in the negative amount of $173,499.00 for the FY19 Water and Wastewater … $173K Grand Prairie, TX

All 8 records for Excel 4 Construction LLC →

Committee
Engineering
Introduced
July 7, 2017
On agenda
July 18, 2017
Passed
July 18, 2017