Ordinance amending the FY 2016/17 Capital Improvement Project Budget; Change Order/Amendment No. 8 with Lee Lewis Construction, Inc. for Epic and Epic Waters in the amount of $252,377 for low voltage/fiber pathway, domestic water sub-meter, revised retaining wall detail at safety walls, credit for eliminated HVAC pumps, 8” domestic water line stop, Oncor service for site amenities and additional construction testing; and ratification of change of funding source on Change Order/Amendment No. 7

Ordinance Adopted Introduced April 21, 2017

What this record is

Held by
Lee Lewis Construction, Inc 26 records across this site
Amount
$252K
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Lee Lewis Construction, Inc also holds

To approve a decrease to the current awarded contract amount of $13,568,203 by $131,544.25 for a total contract amount of $13,436,658.75 for 050 - Tom… $13.6M Plano, TX Discuss, consider and/or take action to authorize the County Judge to sign an Agreement for Construction Manager-At-Risk with Lee Lewis Construction, … Lubbock County, TX Discuss, consider and/or take action to authorize the County Judge to sign Amendment Two to the Agreement for Construction Manager-At-Risk with Lee Le… Lubbock County, TX Discuss, consider and/or take action to authorize the County Judge to sign Change Order #1 with Lee Lewis Construction, Inc. to add an additional seve… Lubbock County, TX Discuss, consider and/or take action to authorize the County Judge to sign the First Amendment to the Contract for Construction with Lee Lewis Constru… Lubbock County, TX

All 26 records for Lee Lewis Construction, Inc →

Committee
Engineering
Introduced
April 21, 2017
On agenda
May 2, 2017
Passed
May 2, 2017
Enacted
May 2, 2017
Enactment no.
ORD 10252-2017