26-90A

Authorize an increase in the construction services contract with HQS Construction, LLC to compensate the contractor for additional work required by the Texas Department of Transportation (TxDOT), 12 months of additional traffic control maintained during TxDOT’s signal work at the Highland Road and Ferguson Road intersection and remobilization necessary to complete the construction of Streetscape/Urban Design Group 17-7006 - Not to exceed $319,746.44, from $2,642,465.00 to $2,962,211.44 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Fund) ($281,533.94), Equity Revitalization Capital Fund ($38,212.50) *In alignment with Infrastructure Management Plan.

CONSENT AGENDA Approved Introduced December 29, 2025
Committee
Department of Transportation and Public Works
Requested by
Department of Transportation and Public Works (TPW)
Introduced
December 29, 2025
On agenda
January 28, 2026
Enactment no.
26-0287; APPROVED

Where it was heard

City Council Jan 28, 2026