docketcity.com
26-90A

Authorize an increase in the construction services contract with HQS Construction, LLC to compensate the contractor for additional work required by the Texas Department of Transportation (TxDOT), 12 months of additional traffic control maintained during TxDOT’s signal work at the Highland Road and Ferguson Road intersection and remobilization necessary to complete the construction of Streetscape/Urban Design Group 17-7006 - Not to exceed $319,746.44, from $2,642,465.00 to $2,962,211.44 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Fund) ($281,533.94), Equity Revitalization Capital Fund ($38,212.50) *In alignment with Infrastructure Management Plan.

CONSENT AGENDA Approved Introduced December 29, 2025
Committee
Department of Transportation and Public Works
Requested by
Department of Transportation and Public Works (TPW)
Introduced
December 29, 2025
On agenda
January 28, 2026
Enactment no.
26-0287; APPROVED

Where it was heard

City Council Jan 28, 2026

Watch Dallas

Say what matters to you — a street, a company, a subject — and we will email you when Dallas files something about it.

Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.

↑ Back to top