26-2306A
Authorize a decrease in the construction services contract with EAR Telecommunications, LLC dba EARTC to de-scope all traffic signal work associated with the intersection of Whitehurst Way and Ferris Branch Boulevard due to the intersection no longer meeting federal warrant requirements for a signalized intersection, including all associated quantities for that intersection - Not to exceed ($409,984.00), from $809,580.00 to $399,596.00 - Financing: Street and Transportation (A) Fund (2024 General Obligation Bond Fund) *In alignment with Vision Zero Plan.
- Committee
- Department of Transportation and Public Works
- Requested by
- Department of Transportation and Public Works (TPW)
- Introduced
- July 14, 2026
- On agenda
- October 14, 2026