Motion to approve a Downtown Development Agreement with Marcos J. Oliveira for improvements to the property located at 523 Taylor Street for a total incentive amount not to exceed $133,500, effective upon signature by the City Manager or designee from the TIRZ #3 Commercial Finish Out (Landlord) and Streetscape and Safety Improvement Program.
What this record is
- Amount
- $134K
- Runs until
- Not stated in the agenda text — the term is normally in the signed agreement, attached to the original item ↗
- Type
- contract
- Field
- Construction
construction contracts in TX that end within a year →
Governments publish the end date in the award. That date is when the
work goes back out to bid, and it is usually stated years ahead.
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Reinvestment Zone No. 3 - Downtown
- Introduced
- February 9, 2026
- On agenda
- February 24, 2026
- Passed
- February 24, 2026
Where it was heard
Reinvestment Zone No. 3 - DowntownWatch what Corpus Christi buys
This is one award. Corpus Christi signs them continuously, and each one names a company and a date it runs out. Say what you sell and we will email you when the next one matches.
Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.