26-0138

One Reading ordinance amending a portion of TIRZ #2 Capital Improvement Projects (CIP) to fully fund the North Padre Island Seawall CIP Project, including the transfer of $2,100,000.00 from the Sand Dollar CIP Project, $300,000.00 from the Crowsnest CIP Project, $2,700,000.00 from the Packery Channel Capital Repairs CIP Project, $300,000.00 from the Packery Channel TDEM CIP Project, $900,000.00 from the Whitecap Effluent Waterline CIP Project, and $4,800,000.00 from the CIP reserves for a total amount of $11,100,000.00 reallocated to the North Padre Island Seawall CIP Project; and amending the FY 2026 Capital Budget.

Emergency Ordinance Passed Introduced January 21, 2026
Committee
City Council
Introduced
January 21, 2026
On agenda
January 27, 2026
Passed
January 27, 2026
Enacted
January 27, 2026
Enactment no.
033851

Where it was heard

City Council Jan 27, 2026 passed on emergency Pass