docketcity.com
23-2070

Ordinance authorizing a Wastewater Trunk Line Construction and Reimbursement Agreement up to $1,978,937.16 with MPM Development to construct a wastewater trunk line for the proposed residential development located off the northwest side of Haven Dr. and Warrior Rd. intersection, also known as Haven Subdivision, requiring construction completion within 24 months; and authorizing future transfer and appropriation of Water and Wastewater Trust Fund revenue up to $1,978,937.16 to reimbursement the developer in accordance with the agreement. (District 1)

Public Hearing / First Reading Withdrawn Introduced January 2, 2024
Committee
City Council
Introduced
January 2, 2024
On agenda
February 13, 2024
Passed
February 15, 2024