7459
Consider Authorizing The City Manager To Execute Change Order No. 3 With Gomez Floor Covering, Inc. dba GFC Contracting For The City Hall Basement Remodel Project In An Amount Not To Exceed $28,138.00 Increasing The Total Project Contract To $961,946.00.
What this record is
- Held by
- Gomez Floor Covering, Inc 8 records across this site
- Amount
- $28K
- Runs until
- no end date published in this record
- Type
- amendment
Read automatically from the title of the official record. The source document below is authoritative.
Gomez Floor Covering, Inc also holds
Consider Authorizing The City Manager to Execute Change Order No. 04 With Gomez Floor Covering, Inc. Dba GFC Contracting, For Additional Work On The C… Consider Authorizing The City Manager To Enter Into An Agreement With Gomez Floor Covering, Inc. Pursuant To Competitive Sealed Proposal (CSP) 25-017 … Consider Authorizing The City Manager To Execute A Construction Contract With Gomez Floor Covering, Inc. DBA GFC Contracting For The Carrollton City H… ** Bid No. 2022-081 - Annual Contract for Carpet, Tile, and Miscellaneous Flooring Materials and Services - Facilities Management - Gomez Floor Coveri… Approving the Purchase from Gomez Floor Covering, Inc., Dba GFC Contracting, for the Carpet and Vinyl Tile Replacement at the Valley View Municipal Co…All 8 records for Gomez Floor Covering, Inc →
- Committee
- City Council
- Requested by
- Engineering Department
- Introduced
- November 10, 2025
- On agenda
- November 18, 2025
- Passed