Consider Authorizing The City Manager To Approve A Construction Contract With J.R. Stelzer Co. For The Hebron Water Tower, Columbian Club Pump Station 5M & 6M Ground Storage Reservoirs & Downtown Silos Painting Projects In An Amount Not To Exceed $3,126,958.00.
What this record is
- Amount
- $3.13M
- Runs until
- no end date published in this record
- Type
- contract
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- City Council
- Requested by
- Engineering Department
- Introduced
- July 25, 2024
- On agenda
- August 6, 2024
- Passed
- August 6, 2024