20-0256

Consideration Of Amendment No. 3 To The Professional Services Agreement (COF 2015-0052) For The East McEwen Drive Phase 4 Improvements - Final Design Project, With Sullivan Engineering Inc., In An Amount Not To Exceed $82,589.32. (CIC 2/27/20, 3-0)

Contract/Agreement Passed Introduced March 2, 2020

What this record is

Amount
$83K
Runs until
no end date published in this record
Type
amendment
Field
Professional services

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Board of Mayor & Aldermen
Requested by
Engineering
Introduced
March 2, 2020
On agenda
March 10, 2020
Passed
March 10, 2020

Where it was heard

Board of Mayor & Aldermen Mar 10, 2020 approved