docketcity.com
20-0188

Consideration of Change Order Number 2 (COF 2018-0252), Final Change Order, for the Jim Warren City Park Tennis Court Reconstruction Project for an Increase in the Amount of $19,449.15.

Contract/Agreement Agenda Ready Introduced February 6, 2020

What this record is

Amount
$19K
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Capital Investment Committee
Requested by
Engineering
Introduced
February 6, 2020
On agenda
February 27, 2020
Passed
February 27, 2020

Where it was heard

Capital Investment Committee Feb 27, 2020 approved Pass