docketcity.com
19-1294

Consideration Of Change Order No. 1 To COF Contract No. 2019-0104, (Final Change Order And Project Closeout) To The Construction Contract With Sessions Paving Co. For The Hillsboro Road Driveway Paving Project. (WS 1/14/20)

Contract/Agreement Passed Introduced December 13, 2019
Committee
Board of Mayor & Aldermen
Requested by
Engineering
Introduced
December 13, 2019
On agenda
January 28, 2020
Passed
January 28, 2020

Where it was heard

Board of Mayor & Aldermen Jan 28, 2020 approved Work Session Jan 14, 2020 referred as a Consent Item