Consideration of the Final Reconciling Change Order to the Construction Contract (COF Contract No. 2014-0288) with Revere Control Systems, Inc. for the Water Distribution and Collection System SCADA Improvements Project for a Decrease in the Amount of $116,828.98 and a Time Extension of 297 calendar days. (01/24/19 CIC 4-0)
What this record is
- Held by
- Revere Control Systems, Inc 4 records across this site
- Amount
- $117K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Revere Control Systems, Inc also holds
Resolution #150-2026 authorizing the City Manager to execute a contract with Revere Control Systems, Inc. for as-needed instrumentation and controls s… Approve Agreement 22-103, Work Authorization No. 18 with Revere Control Systems, Inc. for the Southwest Regional Wastewater Treatment Facility (WWTF) … *Consideration of Resolution 2016-56: A Resolution Awarding the Construction Contract (COF Contract No 2014-0288) To Revere Control Systems, Inc. In …- Committee
- Board of Mayor & Aldermen
- Requested by
- Water Management
- Introduced
- January 8, 2019
- On agenda
- February 12, 2019
- Passed