docketcity.com

City Commission

September 15, 2025 Final

Agenda — 5 items

  1. Approval of Change Order No. 2 - 69 x 115 / 13.8 kV Power Transformer - Green Substation
  2. Approval of Change Order No. 1 - City Library Ramp Project - Kesteloot Excavation and Dirt Work Services.
  3. Approval of Change Order No. 2 - North Egan Avenue Reconstruction - Winter Contracting, LLC
  4. Award Bid #983 - Green Substation Site Grading
  5. Award Bid #985 - Furnishing Major Materials - Green Substation