Discussion and possible action regarding Change Order No. 2 on ODOT Project STP-255C (613) CO - Bridge 30. This change order replaces the Revetment Mattress pay item with Filter blanket and Rip Rap. The total value for the change order is $45,299.80 (Forty-Five Thousand Two Hundred Ninety-Nine Dollars and 80/100). The County share will be reflected in the final cost apportionment of the project Requested by Stacey Trumbo, PE, County Engineer.

Departmental Items Agenda Ready Introduced September 9, 2024

What this record is

Amount
$45K
Runs until
no end date published in this record
Type
amendment
Field
Professional services

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Board of County Commissioners
Requested by
Engineering
Introduced
September 9, 2024
On agenda
September 11, 2024

Where it was heard