2024-0689
Discussion and possible action regarding Change Order No. 3 on ODOT Project STP-155C(750)CI. Widen and resurface county road (Macarthur Boulevard): at the intersection of Covell Road near Edmond. Project Length=0.471 Mile. This Change Order establishes the final quantity for each item on the original contract and resulted in a contract underrun. Requested by Stacey Trumbo, PE, County Engineer.
- Committee
- Board of County Commissioners
- Requested by
- Engineering
- Introduced
- February 29, 2024
- On agenda
- March 4, 2024
Where it was heard
Board of County CommissionersWatch Oklahoma County
Say what matters to you — a street, a company, a subject — and we will email you when Oklahoma County files something about it.
Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.