Consider approving the final Change Order No.3 with an overall deduction of $14,250.00 for Project PW2101 Landfill Cells 6 & 7, as constructed by 4X Construction Group, LLC, thereby releasing the retainage in the amount of $204,865.39 and placing the Maintenance Bond into effect.