Consider and take action approving Change Order 1 increasing the contract by $1,037,837.91 and adding 180 calendar days to the project time for WWTP Phase I Improvements Project PU2103 as constructed by Wynn Construction, Co, to replace three unserviceable blowers with Four new blowers at the WWTP, with a final contract amount of $84,817,891.91, a 1.2% increase to the original contract.

Consent Agenda Agenda Ready Introduced April 26, 2024

What this record is

Amount
$84.8M
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
City Council
Introduced
April 26, 2024
On agenda
May 14, 2024

Where it was heard

City Council May 14, 2024