Consider and take action approving Change Order 1 increasing the contract by $1,037,837.91 and adding 180 calendar days to the project time for WWTP Phase I Improvements Project PU2103 as constructed by Wynn Construction, Co, to replace three unserviceable blowers with Four new blowers at the WWTP, with a final contract amount of $84,817,891.91, a 1.2% increase to the original contract.