docketcity.com
24-1357

Consider and take action approving Change Order 1 reducing the contract by $706,852.11, accepting project in the final contract amount of $1,733,921.17 and placing the Maintenance Bond into effect the for Industrial Water Main Extension Phase I PU2306 as constructed by M&T Septic and Backhoe Service, INC.

Consent Agenda Approved Introduced March 6, 2024
Committee
City Council
Introduced
March 6, 2024
On agenda
March 26, 2024
Passed
March 26, 2024
Enacted
March 26, 2024

Where it was heard

City Council Mar 26, 2024

Watch Lawton