25-76
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE A CHANGE ORDER TO THE CONTRACT WITH THOMPSON ELECTRIC INC. FOR CONSTRUCTION SERVICES FOR THE EASTSIDE SUBSTATION TRANSFORMER REPLACEMENT PROJECT; AND DECLARING AN EMERGENCY. Brief Description: This project involves the completion of the required construction services to install the transformer, voltage regulators and related equipment needed to complete this project.
- Committee
- City Council
- Requested by
- Public Works Department
- Introduced
- April 7, 2025
- On agenda
- May 6, 2025
- Passed
- May 6, 2025