25-5
A RESOLUTION AUTHORIZING THE CITY MANAGER TO ADVERTISE FOR BIDS AND TO ENTER INTO A CONTRACT FOR THE MEADOWOOD LANE CULVERT IMPROVEMENT PROJECT WITH THE LOWEST AND BEST BIDDER. Brief Description: This project involves replacing two (2) existing culverts under a private drive called Meadowood Lane. The culverts carry water from two stormwater management ponds in Village West Subdivision, behind homes on Prescott Drive and Stratford Road, that flow west across Meadowood Lane. During heavy rains, the existing culverts are inundated causing overland flooding of shared use driveway, restricting emergency vehicle access. The project includes installation of larger culverts and concrete driveway replacement.
- Committee
- City Council
- Requested by
- Engineering Department
- Introduced
- December 17, 2024
- On agenda
- January 21, 2025
- Passed
- January 21, 2025