A RESOLUTION AUTHORIZING THE CITY MANAGER TO ENTER INTO AN EMERGENCY AGREEMENT WITH MAGNETECH INDUSTRIAL SERVICES, INC. FOR THE INSPECTION AND DIAGNOSIS OF A 12.47 KV TRANSFORMER AT THE CITY’S SOUTHSIDE SUBSTATION; AND DECLARING AN EMERGENCY. Brief Description: On August 13th, the City of Hudson experienced a substantial lightning storm in the area of our Southside Substation. The storm tripped one of our main transformers at the substation. The transformer has been out of service since August 13th. The transformer was tested after the storm, and it was determined that the transformer cannot be re-energized. The distribution circuit that this transformer served was transferred to another substation, and the system is still being supplied from that location, which reduces the reliability of our system.
- Committee
- City Council
- Requested by
- Engineering Department
- Introduced
- August 26, 2025
- On agenda
- September 2, 2025
- Passed
- September 2, 2025