24-43
A RESOLUTION AUTHORIZING THE CITY MANAGER TO ADVERTISE FOR BIDS AND TO ENTER INTO A CONTRACT FOR THE ALISA COURT DRAINAGE DITCH PROJECT WITH THE LOWEST AND BEST BIDDER. Brief Description: Residents on Alisa Court off of Nicholson Drive notified the City that during heavier rains, flows along the drainage ditch adjacent to their property are causing erosion. The Alisa Court Drainage Ditch Project involves adding channel protection along a sharp bend in the ditch and removing obstructions and minor regrading to reduce ditch flooding and sediment transport, with an estimated project cost of $250,000 including a 10% contingency.
- Committee
- City Council
- Requested by
- Engineering Department
- Introduced
- March 18, 2024
- On agenda
- April 16, 2024
- Passed
- April 16, 2024