3182-2025
To modify the professional engineering services contract with Murphy Epson, Inc., for the Lead Service Line Outreach project; to authorize an amendment to the 2025 Capital Improvement Budget; to authorize a transfer of cash and appropriation within the Water Bond Fund; to authorize an expenditure of up to $638,046.88 from the Water Bond Fund to pay for the contract modification; and to declare an emergency. ($638,046.88)
- Committee
- Public Utilities & Sustainability Committee
- Requested by
- Utilities Drafter
- Introduced
- November 17, 2025
- On agenda
- December 8, 2025
- Passed
- December 10, 2025