2093-2025
To authorize the Director of the Department of Public Utilities to enter into a construction contract with Kenmore Construction Co., Inc., for the Barnett Rd Storm Sewer Improvements & the Barnett Rd Water Main Improvements project; to authorize an amendment to the 2025 Capital Improvement Budget; to appropriate funds within the OWDA Storm Sewers Fund and the Water - Water Fresh Market Rate Fund; to transfer cash and appropriation within the Storm Bond Fund; to make this ordinance contingent upon the Ohio Water Development Authority approving both loans for this project; and to authorize the expenditure of $4,952,844.68 from the OWDA Storm Sewers Fund, the Water - Water Fresh Market Rate Fund, and the Storm Bond Fund to pay for the project. ($4,952,844.68)
- Committee
- Public Utilities & Sustainability Committee
- Requested by
- Utilities Drafter
- Introduced
- July 16, 2025
- On agenda
- September 29, 2025
- Passed
- October 1, 2025