1681-2026
To authorize the Director of Public Utilities to enter into a Guaranteed Maximum Reimbursement Agreement with PREMIER Design + Build Group, LLC for the Intermodal Sanitary Subtrunk Extension Phase 2 project; to amend the 2025 Capital Improvement Budget; to authorize a transfer of cash and appropriation within the Sanitary Bond Fund; to authorize an expenditure of up to $2,560,356.00 from the Sanitary Bond Fund; and to declare an emergency. ($2,560,356.00)
- Committee
- Public Utilities & Sustainability Committee
- Requested by
- Utilities Drafter
- Introduced
- May 29, 2026
- On agenda
- June 22, 2026
- Passed
- June 24, 2026