To authorize the Director of the Department of Public Utilities to enter into a construction contract with BLD Services, LLC, for the Blueprint Hilltop1-Eureka Fremont Lateral Lining Project 6; to authorize an amendment to the 2024 Capital Improvement Budget; to appropriate funds within the Water Pollution Control Loan Fund; to make this ordinance contingent upon the Ohio Water Development Authority approving a loan for this project; and to authorize the expenditure of up to $8,335,316.21 from the Water Pollution Control Loan Fund and the Sanitary Bond Fund to pay for the project. ($8,335,316.21)

Ordinance Passed Introduced April 23, 2025
Committee
Public Utilities & Sustainability Committee
Requested by
Utilities Drafter
Introduced
April 23, 2025
On agenda
June 2, 2025
Passed
June 4, 2025

Where it was heard

Columbus City Council Jun 2, 2025 Approved Pass Columbus City Council May 19, 2025 Read for the First Time