0230-2024
To authorize the Director of the Department of Public Utilities to modify a construction contract for the 2022 Utility Cut Restoration Project with Decker Construction Company for the Division of Water, Division of Power, and Division of Sewerage & Drainage; and to authorize the expenditure of $2,000,000.00 from the Water Operating Fund, $550,000.00, from the Sanitary Sewer Operating Fund, and $50,000.00 from the Electricity Fund. ($2,600,000.00)
What this record is
- Held by
- Decker Construction Company 9 records across this site
- Amount
- $2.60M
- Runs until
- no end date published in this record
- Type
- contract
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Decker Construction Company also holds
To authorize Columbus Water and Power to enter into a construction contract with Decker Construction Company for utility cut and restoration services … To authorize the Director of the Department of Public Utilities to modify a contract for the 2022 Utility Cut Restoration Project with Decker Construc… To authorize the Director of the Department of Public Utilities to modify a contract for the 2022 Utility Cut Restoration Project with Decker Construc… To authorize the Director of Public Service to enter into contract with Decker Construction Company for the Roadway - Utility Cut and Repair 2025 serv… To authorize the Director of the Department of Public Utilities to enter into a service agreement with Decker Construction Company for the 2022 Utilit…All 9 records for Decker Construction Company →
- Committee
- Public Utilities & Sustainability Committee
- Requested by
- Utilities Drafter
- Introduced
- January 11, 2024
- On agenda
- March 25, 2024
- Passed
- March 27, 2024