25-282
SUPPLEMENTAL BOND RESOLUTION OF THE COUNTY OF ALBANY, NEW YORK, DATED JULY 14, 2025, STATING THE ESTIMATED MAXIMUM COST OF THE “CORE SWITCH, TELEPHONE REPLACEMENT AND DATA CENTER PROJECT” IS $2,795,000, APPROPRIATING AN ADDITIONAL $650,000 FOR SAID PROJECT, AND AUTHORIZING THE ISSUANCE OF $650,000 BONDS OF SAID COUNTY TO FINANCE SAID ADDITIONAL APPROPRIATION
- Committee
- Audit and Finance Committee
- Introduced
- May 28, 2025
- Passed
- July 14, 2025