21896-26a

Award of Task Order No. 10, Agreement No. AGR24-39a for the Purpose of Determining Relay Settings for the New Transformer in White Rock Substation with Transmission & Distribution Services, LLC in the Amount of $157,262, plus Applicable Gross Receipts Tax for the Term of 180 Days

Construction Contract Consent Introduced June 25, 2026
Committee
Board of Public Utilities
Requested by
Department of Public Utilities
Introduced
June 25, 2026
On agenda
July 22, 2026

Where it was heard

Board of Public Utilities Jul 22, 2026