docketcity.com
21647-26a

Approval of the Reinstatement of Contract for IFB 25-31 for the Bayo NP Booster Station Rehabilitation Project including the two prior change orders in the Amount of $1,427,586.41 plus NMGRT and Approval of Change Order No. 3 with TLC Company, Inc. in the amount of $34,983.25 plus NMGRT with a New Final Completion Date of June 30, 2026

Construction Contract Consent Introduced April 28, 2026
Committee
Board of Public Utilities
Requested by
Department of Public Utilities
Introduced
April 28, 2026
On agenda
May 6, 2026

Where it was heard

Board of Public Utilities Work Session May 6, 2026