21410-26a

Award of Task Order No. 15 under AGR22-18e with R&M Construction for the Purpose of Drilling Five Piers in the White Rock Substation for the Transformer Replacement Project in the Amount of $463,657.50, add a 10% project contingency of $46,366 plus Applicable Gross Receipts Tax for the Term of 90 Days.

Construction Contract Consent Introduced March 4, 2026

What this record is

Amount
$464K
Runs until
no end date published in this record
Type
award
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Board of Public Utilities
Requested by
Department of Public Utilities
Introduced
March 4, 2026
On agenda
April 1, 2026

Where it was heard

Board of Public Utilities Work Session Apr 1, 2026