Award of Task Order No. 15 under AGR22-18e with R&M Construction for the Purpose of Drilling Five Piers in the White Rock Substation for the Transformer Replacement Project in the Amount of $463,657.50, add a 10% project contingency of $46,366 plus Applicable Gross Receipts Tax for the Term of 90 Days.
What this record is
- Amount
- $464K
- Runs until
- Not stated in the agenda text — the term is normally in the signed agreement, attached to the original item ↗
- Type
- award
- Field
- Construction
construction contracts in NM that end within a year →
Governments publish the end date in the award. That date is when the
work goes back out to bid, and it is usually stated years ahead.
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Board of Public Utilities
- Requested by
- Department of Public Utilities
- Introduced
- March 4, 2026
- On agenda
- April 1, 2026
Where it was heard
Board of Public Utilities Work SessionWatch what Los Alamos County buys
This is one award. Los Alamos County signs them continuously, and each one names a company and a date it runs out. Say what you sell and we will email you when the next one matches.