21410-26a
Award of Task Order No. 15 under AGR22-18e with R&M Construction for the Purpose of Drilling Five Piers in the White Rock Substation for the Transformer Replacement Project in the Amount of $463,657.50, add a 10% project contingency of $46,366 plus Applicable Gross Receipts Tax for the Term of 90 Days.
What this record is
- Amount
- $464K
- Runs until
- no end date published in this record
- Type
- award
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Board of Public Utilities
- Requested by
- Department of Public Utilities
- Introduced
- March 4, 2026
- On agenda
- April 1, 2026