21410-26
Award of Task Order No. 15 under AGR22-18e with R&M Construction for the Purpose of Drilling Five Piers in the White Rock Substation for the Transformer Replacement Project in the Amount of $463,657.50, add a 10% project contingency of $46,366 plus Applicable Gross Receipts Tax for the Term of 90 Days