docketcity.com
R-26-051

Resolution of the Mayor and Council of Princeton Authorizing a Final Change Order in the Amount of -$231,360.21 and Authorizing a Final Payment of $270,641.45, Resulting in a Final Contract Amount of $4,071,410.95, and the Release of Performance Bond for the Phase II Roadway Improvements to Witherspoon Street project to S. Brothers, Inc. and Acceptance of a Maintenance Bond in the Amount of $581,750.43.

Resolution Passed Introduced February 3, 2026
Committee
Mayor and Council of Princeton
Requested by
Engineering
Introduced
February 3, 2026
On agenda
February 9, 2026
Passed
February 9, 2026

Where it was heard

Mayor and Council of Princeton Feb 9, 2026 adopted Pass