23-4676
Change Order No. 1 with Johnson and Schock Excavating, LLC in the amount of $80,000.00 and a 14-day time extension for Project No. WA2507.
What this record is
- Held by
- Johnson and Schock Excavating, LLC 4 records across this site
- Amount
- $80K
- Runs until
- Not stated in the agenda text — the term is normally in the signed agreement, attached to the original item ↗
- Type
- amendment
- Field
- Construction
- Compared to
- $33K – $75K the middle half of 4 other Johnson and Schock Excavating, LLC contracts; median $75K
construction contracts in ND that end within a year →
Governments publish the end date in the award. That date is when the
work goes back out to bid, and it is usually stated years ahead.
Read automatically from the title of the official record. The source document below is authoritative.
Johnson and Schock Excavating, LLC also holds
Change Order No. 2, Final Balancing Change Order with Johnson and Schock Excavating LLC in the amount of $33,399.52 for LSLR Project No. WA2507. Change Order No. 1, Final Balancing Change Order with Johnson and Schock Excavating LLC in the amount of $74,622.75 for LSLR Project No. WA2504. Change Order No. 1 with Johnson and Schock Excavating, LLC in the amount of $28,000.00 and a 7-day time extension for Project No. WA2509.- Committee
- City Commission
- Requested by
- Jodi Kosienski
- Introduced
- July 30, 2026
- On agenda
- August 3, 2026
- Passed
- August 3, 2026
Where it was heard
City CommissionWatch what Fargo buys
This is one award. Fargo signs them continuously, and each one names a company and a date it runs out. Say what you sell and we will email you when the next one matches.
Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.