Approval of Capital Project Amendment No.25CPA017 to Support the Snow Hill Road Pump Station and Force Main Replacement Capital Project (47302635DC149), as well as Execution of the Design-Builder “Guaranteed Maximum Price #4.3” Contract in the amount of $6,659,581.

Action Item Consent Agenda Introduced October 11, 2024

What this record is

Amount
$6.66M
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Board of County Commissioners
Introduced
October 11, 2024
On agenda
November 12, 2024

Where it was heard